USGS CMG-WR Field Schedule (MOP)

Skip navigational links
Search InfoBank
Home tab Atlas tab Activities tab FACS tab Geology School tab More tab More tab FACS tabs
   
New Field Work: GE ( Future  Present   Past )    Field Schedules: ( Santa Cruz / Menlo Park   St. Petersburg   Woods Hole )
Descriptions: Before Activity   During Activity   After Activity   Overview Log   Crew Log   Equipment Log   Navigation Log   Operation Log  
Downloadable Forms: Overview Log (doc)  
Appendix: FACS Coordinators   Day of Year   Activity ID definition   Improving data sharing to improve science  (from MMI)   Crew Log (txt)   Equipment Log (txt)   Navigation Log (txt)   Operation Log (txt)  
   

Legend
planned completed pending funding special

FY08 PROJECT CHIEF STATUS PROJECT Project # FACS ID DATES EST. DURATION SHIP PROGRAM Notes
                     
1 Cochrane completed Ano Nuevo to Bolinas   F-3-07-NC October 1 - 23 14 days Fulmar bottom camera, video groundtruthing Kvitek/CCC
2 Field/Storlazzi completed Guam   B-2-07-WP October 2 weeks   CTD/OBS/PAR redeploy  
3 Hart/Finlayson completed San Andreas Rsvr   F-2-07-CA Nov 5 - 21 3 days Frontier SwathPlus SF PUC
4 Lacy/Rubin completed Possession Sound   K-4-07-PS Nov 12 - 16     deploy tripods (?) Ferreira, Williams, Grover
5 Prouty completed Molokai   A-1-07-MK Nov. 26 - Dec.1       Reiss
6 Noble/Sherwood completed Palos Verdes   S-4-07-SC Dec 4 - 8 2 weeks Sproul 4 tripods, 3 moorings EPA; 4 mo deployment
7 Hanes completed SF Crissy Field & Ocean Beach AZSX5 S-1-08-SF Jan 14-29   Mussel Point & Snavely deploy tripod, profiling Bodega Bay ML
8 Field/Storlazzi completed Guam   B-1-08-WP Jan-Feb 2008 2 weeks none CTD/OBS/PAR recover  
9 Kooker/Grover completed Monterey Bay 0G4A0   Feb - Mar 14 days Snavely shakedown SwathPlus and CA state mapping Monterey Cyn to Ano Nuevo
10 Chezar completed Grand Canyon   R-1-08-GC Jan 28 - Feb 18   raft eyeball  
11 Barnard completed Santa Barbara   S-V1-08-CA Feb 18-22   jetski    
12 Chezar completed Grand Canyon   R-2-08-GC Mar 10 - April 4   raft eyeball Logan
13 Lacy completed Possession Sound   K-4-07-PS Feb 18-22   Karluk recover # 4 Grover, Williams
14 Sherwood/Ferreira completed Palos Verdes   S-W1-08-SC Feb 25 - 29 2 days Sea Watch slow corer WH personnel
15 Kayen/Minasian completed Sapporo, Japan U. Ore. L-S1-08-JP March 1 - 10 10 days na SASW, LIDAR U. Oregon
16 Finlayson/Kooker completed Monterey Bay 0G4A0 S-2-08-MB Mar 3 - 7   Snavely Swath testing P. Byham
17 Barnard/Reiss completed Morro Bay COMA2   Mar 17-21 3 days   jetski training  
18 Lorenson completed Santa Barbara 0LAX1 S-1A-08-SC Mar 13-18 3 days Shearwater SwathPlus WH support/Worley
19 Lorenson completed Santa Barbara 0LAX1 S-1B-08-SC Mar 16-18 3 days Zephyr ROV WH ROV/Borden
20 Finlayson/Hart underway Crystal Springs Rsvrs SFPUC CRADA F-1-08-CA April 7-18 8 to 10 days Frontier Swathplus SF PUC Gabel
21 Childs/Hart planned Santa Cruz 0G4A0 S-4-08-MB Mar-Apr 2 days Snavely calibrate sparker/Chirp need RTK units & calibrated phone
22 Xu/Noble/Sherwood planned Hueneme Canyon C5BE6 S-R3-08-SC April 1 - 10   Sproul recover Palos Verdes and Hueneme Cyn Elfers, Gonzales
23 Lacy/Rubin planned Santa Cruz wharf   W-D1-08-MB June-July   none seafloor observatory Grover, Hatcher
24 Grossman planned Skagit River Delta AZZB0 W-1-08-PS Apr 14 - 18 7 days   waverunners; sed grabs WA DECY RTK-DGPS, Gelfenbaum, tbd
25 Storlazzi planned Monterey Bay   T-D1-08-MB April 1-2 days Pt. Sur deploy tripod  
26 Lee/ Edwards/ planned S. California   B-1-08-SC Apr 15 - 25 10 days OSV Bold boxcoring Alan Ota/EPA
26 Ryan/Conrad planned S. California   B-2-08-SC Apr 25 - May 1 6 dayss OSV Bold minisparker/ Chirp, boxcore Alan Ota/EPA
27 Warrick planned Offshore Tijuana River estuary C5BE1? S-5-08-SC April 28 - May 16 19 days Snavely SwathPlus/Chirp/camera Baseline mapping
28 Hanes planned Golden Gate   X-1-08-SF May 22 - June 6 2 days tbd recover tripod, profiling Bodega Bay ML
29 Grossman planned Skagit River Delta   B-1-08-PS Apr 5 days   deploy WRD ADCP, 5 partner Mcats Pending funding, no MarFac
30 Grossman planned Skagit River Delta   X-1-08-PS May-June 5 days   deploy WRD ADCP, 5 partner Mcats Pending funding, no MarFac support
31 Johnson/Watt planned Hosgri fault survey (Morro Bay) C4AE0 S-6-08-SC June 9-27 19 days Snavely minisparker/chirp/SwathPlus after Tijuana River; PG&E CRADA add-on w/ GUMP maggie
32 Johnson planned Santa Barbara   S-7-08-SC June 28- Jul 1 4 days Snavely Chirp/minisparker CA mapping
33 Grossman planned Skagit Bay AZZB0 K-1-08-PS Jun-Jul 5 days Karluk (or UW R/V Barnes) vibracore, gravity core O'Toole, Grover
34 Grossman pending funding Bellingham Bay ofa K-2-08-PS Jun-Jul 3 days Karluk Chirp only w/ OFA funding and time available
35 Grossman pending funding Skagit River Delta AZZB0 X-2-08-PS Jun-Jul 10 days   IRIS bathy/CHIRP, ADCP Pending ONR funding WH support for IRIS
36 Dartnell planned CA state waters mapping Goleta to Gaviota 0LDB4 S-8-08-SC Jul 8 - 23 14 days Snavely SwathPlus/Chirp after Morro Bay; 117 kHz transducers
37 Edwards/Cochrane planned Stinson Beach to Bodega Bay 0LDB4 S-9-08-NC tbd 7 days Snavely camera groundtruthing MT/ET
38 Storlazzi planned Monterey Bay   T-R1-08-MB late July 1-2 days Pt. Sur recover # 25  
39 Johnson/Cochrane planned Oregon state waters mapping (Seaside-Tillamook Head?) 0LD S-10-08-WO Aug 11 - 27 16 days Snavely SwathPlus/Chirp  
40 Gelfenbaum planned Elwha   W-2-08-PS Aug-Sept 3 weeks jetskis jetski mapping  
41 Edwards/Cochrane planned Bodega Bay to Pt. Arena 0LDB4 F-2-08-NC Sept 1 - 9 8 days Fulmar groundtruthing MT/ET
42 Edwards/Cochrane proposed Bodega Bay to Pt. Arena 0LDB4   Sept 8 days leased boat groundtruthing MT/ET
43 Hutchinson/Childs/Hart planned Arctic na H-1-08-AR September 4 - 30   USCG Healy LotS geophysics Canadian coop; WH techs
44 Hanes planned Crissy Marsh & GG AZSX5 S-11-08-SF Sept 8 - 30 4-6 days Snavely SwathPlus  
45 Hanes planned Crissy Marsh & GG AZSX5 S-11-08-SF Sept 8 - 30 6-8 days Snavely ADCP-CTD  
46 Hanes planned Crissy Marsh & GG AZSX5 S-11-08-SF Sept 8 - 30 2-4 days Snavely grab sampling  
47 Dartnell proposed Santa Barbara Channel 0LDA1 S-1C-08-SC Sept 29 - Oct 8 10 days Shearwater groundtruth / camera MT/ET
48 Draut/Hart planned SB Channel C4AE1 M-2-08-SC Nov 5 - 21 11 days at sea Melville minisparker/Chirp Nicholson/UCSB/Scripps/OSU
49 Edwards/Cochrane planned Bodega Bay to Pt. Arena 0LDB4 X-3-08-NC Oct 18 days SRVx or rental groundtruthing MT/ET
50 Cochrane planned CA state waters mapping Monterey Canyon to Ano Nuevo 0LD S-12-08-MB Nov-Dec 21 days Snavely SwathPlus/Chirp  
                     
                     
                     
FABRICATION / OTHER                    
1 Lacy planned modify tripod for seafloor observatory and poking eyeball             O'Toole, Hatcher
3 Childs planned test operation of coring winch and air compressor van   none         O'Toole
2 Childs/Hart planned maintenance Bauer compressor and small airguns             O'Toole, Elfers, Grover