Comment: 16:52 - 17:32 (00:40)
Source: Annenberg/CPB Resources - Earth Revealed - 20. Running Water II: Landscape Evolution
Keywords: "Old River", dam, "U.S. Army Corps of Engineers", "Old River Control Project", river, "Mississippi River", "Atchafalaya River", "navigational lock", flow-rate
|
Our transcription: First, the Old River channel was dammed; this meant that the only natural connection between the Atchafalaya and the Mississippi was closed. Since the Corps did not want to disrupt boat traffic between the two Rivers, a navigational lock was built on Old River at a cost of $15 million. To enforce the mandated 70/30 flow-rate, construction began on two control structures at a combined cost of $15 million. These structures were completed and operational by 1963.
|